Progress of construction works in B4 building – February 2015


Warsaw, 10 March 2015

FPP informs that:

B4 building is 45% complete. The excavation , drainage, reinforced concrete structures and insulation of the underground parts are 100% completed, the backfill is 99% complete, the bricklaying – 90%, the roof insulation – 60%, external systems (sewage system and storm water drainage, water supply) are 80% complete, sanitary systems and ventilation are 20% complete, whereas the electrical systems are 10% complete.

Here you can see how the buildings look now.