Progress of construction works in B4 building – March 2015

Warsaw, 7 April 2015

FPP informs that:

B4 building is 48% complete. The excavation , drainage, reinforced concrete structures and insulation of the underground parts are 100% completed, the backfill is 99% complete, the bricklaying – 95%, the roof insulation – 70%, external systems (sewage system and storm water drainage, water supply) are 80% complete, sanitary systems and ventilation are 30% complete, whereas the electrical systems are 20% complete.