Progress of construction work at building B4 (June 2015)

Warsaw, 15 June 2015

FPP hereby informs that:

The work progress in buildings B4 is 61%. The excavation is executed in 100%, drainage – 100%, reinforced concrete structure – 100%, insulation for the underground part – 100%, backfills – 100%, masonry works – 100%, roof insulation – 95%, external networks (storm and sanitary drainage, water supply) – 90%, sanitary systems and ventilation – 50%, electrical systems – 55%, plasters – 50%, outer balustrades – 50%, windows – 90%, aluminium joinery – 50%, façade – 30%, insulation for terraces and balconies – 50%, skim coats – 30%.