News

2015-07-16

Progress of construction work at building B4 (July 2015)

Warsaw, July 15th2015.

FPP hereby informs:

The current progress rate for the B4 buildings is 66%. The excavation has been completed in 100%, drainage in 100%, reinforced concrete construction in 100%, underground section insulations in 100%, excavation fills in 100%, masonry work in 100%, roof insulation in 95%, external installations (storm and sanitary sewage, water supply) in 95%, sanitary installations and ventilation in 55%, electrical installations in 60%, plaster coats in 75%, external railing in 60%, windows in 95%, aluminum joinery in 76%, facade in 50%, terraces and balconies insulation in 80%, floor toppings in 50%, garage floor in 5%, painting of the flats in 5%. Beginning July 9th, we have started the elevators assembly.

You are welcome to view the most recent photographs on our website.

Sales and Marketing Department





the housing estate plan
Contact | Fadesa Polnord | Privacy Policy | cookies