Progress of construction work at building C2 (September 2015)

Warsaw, 04/09/2015

Ladies and Gentlemen,

The percentage of completion ratio of the buildings C2 is 34%. The reinforced concrete structure has been completed in 95%, the insulation of the underground part of the building in 95%. Backfilling of the building is done in 70%. Wall masonry works have started.